Clayton High School Topping Out Ceremony

October 1 marked a huge milestone for our RDU K-12 team as we celebrated the topping out of Clayton High School. It’s exciting to see a new chapter for the school taking shape, one blue beam at a time. Go Comets!
A few numbers behind the progress:
 
  • 224 days from groundbreaking to topping out
  • 460 days until students begin moving into Phase 1
  • A 17-foot grade change navigated across the site
  • The first project in Johnston County to have an operating school campus alongside this scale of construction
Phase 1 is set for move-in in January 2028, followed by completion of Phase 2 demolition in August 2028.
Scroll to Top